2001 Montana Legislature

About Bill -- Links

SENATE BILL NO. 240

INTRODUCED BY W. MCNUTT, BALES, CLANCY, COLE, DEVLIN, G. FORRESTER, HEDGES, R. HOLDEN, OLSON

Montana State Seal

AN ACT ELIMINATING PROJECT DEVELOPMENT DEADLINES THAT ARE REQUIRED TO QUALIFY FOR REDUCED OIL PRODUCTION TAX RATES FOR CERTAIN OIL WELL ENHANCED RECOVERY PROJECTS; REVISING DEFINITIONS; AMENDING SECTION 15-36-303, MCA; AND PROVIDING AN IMMEDIATE EFFECTIVE DATE.



BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF MONTANA:



     Section 1.  Section 15-36-303, MCA, is amended to read:

     "15-36-303.  Definitions. As used in this part, the following definitions apply:

     (1)  "Board" means the board of oil and gas conservation provided for in 2-15-3303.

     (2)  "Department" means the department of revenue provided for in 2-15-1301.

     (3)  "Enhanced recovery project" means the use of any process for the displacement of oil from the earth other than primary recovery and includes the use of an immiscible, miscible, chemical, thermal, or biological process.

     (4)  "Existing enhanced recovery project" means an enhanced recovery project that began development before January 1, 1994.

     (5)  "Expanded enhanced recovery project" or "expansion" means the addition of injection wells or production wells, the recompletion of existing wells as horizontally completed wells, the change of an injection pattern, or other operating changes to an existing enhanced recovery project that will result in the recovery of oil that would not otherwise be recovered. The project must be developed after December 31, 1993, and before January 1, 2002.

     (6)  "Gross taxable value", for the purpose of computing the oil and natural gas production tax, means the gross value of the product as determined in 15-36-305.

     (7)  "Horizontal drain hole" means that portion of a well bore with 70 degrees to 110 degrees deviation from the vertical and a horizontal projection within the common source of supply, as that term is defined by the board, that exceeds 100 feet.

     (8)  "Horizontally completed well" means:

     (a)  a well with one or more horizontal drain holes; and

     (b)  any other well classified by the board as a horizontally completed well.

     (9)  "Incremental production" means:

     (a)  the volume of oil produced by a new enhanced recovery project, by a well in primary recovery recompleted as a horizontally completed well, or by an expanded enhanced recovery project, which volume of production is in excess of the production decline rate established under the conditions existing before:

     (i)  the commencement of the recompletion of a well as a horizontally completed well;

     (ii) expansion of the existing enhanced recovery project; or

     (iii) commencing a new enhanced recovery project; or

     (b)  in the case of any project that had no taxable production prior to commencing the enhanced recovery project, all production of oil from the enhanced recovery project.

     (10) "Natural gas" or "gas" means natural gas and other fluid hydrocarbons, other than oil, produced at the wellhead.

     (11) "New enhanced recovery project" means an enhanced recovery project that began development after December 31, 1993, and before January 1, 2002.

     (12) "Nonworking interest owner" means any interest owner who does not share in the exploration, development, and operation costs of the lease or unit, except for production taxes.

     (13) "Oil" means crude petroleum or mineral oil and other hydrocarbons, regardless of gravity, that are produced at the wellhead in liquid form and that are not the result of condensation of gas after it leaves the wellhead.

     (14) "Operator" or "producer" means a person who produces oil or natural gas within this state or who owns, controls, manages, leases, or operates within this state any well or wells from which any marketable oil or natural gas is extracted or produced.

     (15) "Post-1999 well" means an oil or natural gas well drilled on or after January 1, 1999, that produces oil or natural gas or a well that has not produced oil or natural gas during the 5 years immediately preceding the first month of qualifying as a post-1999 well.

     (16) "Pre-1999 well" means an oil or natural gas well that was drilled before January 1, 1999.

     (17) "Primary recovery" means the displacement of oil from the earth into the well bore by means of the natural pressure of the oil reservoir and includes artificial lift.

     (18) "Production decline rate" means the projected rate of future oil production, extrapolated by a method approved by the board, that must be determined for a project area prior to commencing a new or expanded enhanced recovery project or the recompletion of a well as a horizontally completed well. The approved production decline rate must be certified in writing to the department by the board. In that certification, the board shall identify the project area and shall specify the projected rate of future oil production by calendar year and by calendar quarter within each year. The certified rate of future oil production must be used to determine the volume of incremental production that qualifies for the tax rate imposed under 15-36-304(5)(e).

     (19)  (a) "Qualifying production" means the first 12 months of production of oil or natural gas from a well drilled after December 31, 1998, drilled after December 31, 1998, or the first 18 months of production of oil or natural gas from a horizontally completed well drilled after December 31, 1998, drilled after December 31, 1998, or from a well that has not produced oil or natural gas during the 5 years immediately preceding the first month of qualifying production.

     (b)  Qualifying production does not include oil production from a horizontally recompleted well.

     (20) "Secondary recovery project" means an enhanced recovery project, other than a tertiary recovery project, that commenced or was expanded after December 31, 1993, and before January 1, 2002, and meets each of the following requirements:

     (a)  The project must be certified as a secondary recovery project to the department by the board. The certification may be extended only after notice and hearing in accordance with Title 2, chapter 4.

     (b)  The property to be affected by the project must be adequately delineated according to the specifications required by the board.

     (c)  The project must involve the application of secondary recovery methods that can reasonably be expected to result in an increase, determined by the board to be significant in light of all the facts and circumstances, in the amount of oil that may potentially be recovered. For purposes of this part, secondary recovery methods include but are not limited to:

     (i)  the injection of water into the producing formation for the purposes of maintaining pressure in that formation or for the purpose of increasing the flow of oil from the producing formation to a producing well bore; or

     (ii) any other method approved by the board as a secondary recovery method.

     (21) "Stripper natural gas" means the natural gas produced from any well that produces less than 60,000 cubic feet of natural gas a day during the calendar year immediately preceding the current year. Production must be determined by dividing the amount of production from a lease or unitized area for the year immediately preceding the current calendar year by the number of producing wells in the lease or unitized area and by dividing the resulting quotient by 365.

     (22) "Stripper oil" means the oil produced from any well that produces less than 15 barrels a day for the calendar year immediately preceding the current year if the average price for a barrel of oil as reported in the Wall Street Journal for west Texas intermediate crude oil during a calendar quarter is less than $30 a barrel. If the price of oil is equal to or greater than $30 a barrel in a calendar quarter, there is no stripper tax rate, including stripper well exemption tax rate, in that quarter. The average price for a barrel is computed by dividing the sum of the daily price for west Texas intermediate crude oil as reported in the Wall Street Journal for the calendar quarter by the number of days on which the price was reported in the quarter. Production must be determined by dividing the amount of production from a lease or unitized area for the year immediately preceding the current calendar year by the number of producing wells in the lease or unitized area and by dividing the resulting quotient by 365.

     (23) "Stripper well exemption" means petroleum and other mineral or crude oil produced by a stripper well that produces 3 barrels a day or less.

     (24) "Tertiary recovery project" means an enhanced recovery project, other than a secondary recovery project, using a tertiary recovery method that meets the following requirements:

     (a)  The project must be certified as a tertiary recovery project to the department by the board. The certification may be extended only after notice and hearing in accordance with Title 2, chapter 4.

     (b)  The property to be affected by the project must be adequately delineated in the certification according to the specifications required by the board.

     (c)  The project must involve the application of one or more tertiary recovery methods that can reasonably be expected to result in an increase, determined by the board to be significant in light of all the facts and circumstances, in the amount of crude oil that may potentially be recovered. For purposes of this part, tertiary recovery methods include but are not limited to:

     (i)  miscible fluid displacement;

     (ii) steam drive injection;

     (iii) micellar/emulsion flooding;

     (iv) in situ combustion;

     (v)  polymer augmented water flooding;

     (vi) cyclic steam injection;

     (vii) alkaline or caustic flooding;

     (viii) carbon dioxide water flooding;

     (ix) immiscible carbon dioxide displacement; or

     (x)  any other method approved by the board as a tertiary recovery method.

     (25) "Well" or "wells" means a single well or a group of wells in one field or production unit and under the control of one operator or producer.

     (26) "Working interest owner" means the owner of an interest in an oil or natural gas well or wells who bears any portion of the exploration, development, and operating costs of the well or wells."



     Section 2.  Effective date. [This act] is effective on passage and approval.

- END -




Latest Version of SB 240 (SB0240.ENR)
Processed for the Web on April 11, 2001 (4:44PM)

New language in a bill appears underlined, deleted material appears stricken.

Sponsor names are handwritten on introduced bills, hence do not appear on the bill until it is reprinted. See the status of this bill for the bill's primary sponsor.

Status of this Bill | 2001 Legislature | Leg. Branch Home
All versions of this bill (PDF Format)
Authorized print version w/line numbers (PDF format)

Prepared by Montana Legislative Services

(406)444-3064