     82-4-433. Bond. (1) A bond required to be filed under this part by the operator must be in a form that the department prescribes, payable to the state of Montana and conditioned upon the operator's full compliance with all requirements of this part, the rules of the board, and the permit. The bond must be signed by the landowner or operator, as appropriate, as principal, and by a good and sufficient corporate surety licensed to do business in the state of Montana, as surety. The bond must be in an amount not to exceed the costs of restoration required by this part as determined by the department. The amount of the bond may not be less than $200 or more than $1,000 an acre unless the department determines, in writing, that the cost of restoration of the land exceeds $1,000 an acre. Upon the cost determination, the bond amount must be set by the department at the cost of restoring the land.
     (2) In lieu of the bond, the operator may deposit with the department cash, government securities, a letter of credit in a form acceptable to the department, or a bond with property sureties in an amount equal to that of the required bond on conditions as prescribed in this part. In the discretion of the department, surety bond requirements may be fulfilled by the operator's posting a bond with land and improvements and facilities located on the land as security, in which event a surety may not be required but the department may require that the amount of the bond be adjusted to reimburse the department for foreclosure costs. The penalty of the bond or amount of cash and securities must be increased or reduced from time to time as provided in this part. The bond or security remains in effect until the affected land has been reclaimed as provided under the permit and the reclamation has been approved and the bond or security has been released by the department. The bond or security may cover only actual affected land and may be increased or reduced to cover only those acreages as remain unreclaimed.
     (3) If the license of a surety upon a bond filed with the department pursuant to this part is suspended or revoked, the operator, within 30 days after receiving notice of the suspension or revocation from the department, shall substitute for that surety a good and sufficient surety licensed to do business in the state. Upon failure of the operator to make substitution of surety, the department may suspend the permit of the operator to conduct operations upon the land described in the permit until the substitution has been made.
     (4) The department shall cause the reclamation of any affected land with respect to which a bond has been forfeited.
     (5) Whenever an operator has completed all of the requirements under the provisions of this part as to any affected land, the operator shall notify the department of the completed requirements. If the board releases the operator from further obligation regarding any affected land, the penalty of the bond must be reduced proportionately.

     History: En. Sec. 9, Ch. 326, L. 1973; amd. Sec. 22, Ch. 39, L. 1977; R.C.M. 1947, 50-1509; amd. Sec. 1, Ch. 138, L. 1983; amd. Sec. 5, Ch. 280, L. 1987; amd. Sec. 3, Ch. 431, L. 1991; amd. Sec. 412, Ch. 418, L. 1995; amd. Sec. 16, Ch. 507, L. 1999.

Previous SectionHelpNext Section