Montana Code Annotated 2009

Clickable Image


     90-4-1003. Energy policy development process. (1) (a) Except as provided for in subsection (1)(b), each interim, the energy and telecommunications interim committee established in 5-5-230 shall review the state energy policy and recommend potential changes to the state energy policy, pursuant to subsection (2).
     (b) During the 2009-2010 interim, the committee shall consult with a broad representation of stakeholders, including appropriate state agencies and the public, and focus on the following issues to be included in a revised state energy policy:
     (i) increasing the supply of low-cost electricity with coal-fired generation;
     (ii) rebuilding and extending electric transmission lines;
     (iii) maximizing state land use for energy generation;
     (iv) increasing energy efficiency standards for new construction;
     (v) promoting conservation;
     (vi) promoting energy efficiency incentives;
     (vii) promoting alternative energy systems;
     (viii) reducing regulations that increase ratepayers' energy costs; and
     (ix) integrating wind energy.
     (2) Except as provided in subsection (1)(b), the committee shall consult with a broad representation of stakeholders, including appropriate state agencies and the public, in developing the issues to be included within the proposed, revised state energy policy each interim.
     (3) Each biennium, the committee shall forward its recommendations to the legislature and to the appropriate state agencies for adoption.
     (4) In carrying out its responsibilities under this section, the committee shall use its interim budget, as allocated by the legislative council, and rely on the input of locally available experts and staff research to accomplish its responsibilities.

     History: En. Sec. 3, Ch. 242, L. 1993; amd. Sec. 3, Ch. 221, L. 2005; amd. Sec. 2, Ch. 454, L. 2009.