Montana Code Annotated 2023

TITLE 2. GOVERNMENT STRUCTURE AND ADMINISTRATION

CHAPTER 10. STATE AGENCY ACTIONS AFFECTING PRIVATE PROPERTY

Part 1. Private Property Assessment Act

Notice To Public And Interested Persons

2-10-111. Notice to public and interested persons. (1) After an impact assessment has been completed, and regardless of the findings in the assessment, the state agency that performed the impact assessment shall provide notice to the public and interested persons of its intent to engage in the proposed action. The notice must be provided through use of either electronic e-mail lists or postal mail lists to all persons who have elected to be notified of impact assessments and through the use of the state's official internet website used by all state agencies.

(a) The electronic e-mail lists and postal mail lists must be established to allow interested persons to be on lists notifying them of impact assessments of all state agencies or of specific information based on agency name or geographical location of a proposed action and may provide notice based on other criteria that would promote public awareness of proposed actions.

(b) The agency website link must allow access to impact assessments of all state agencies or to specific information based on agency name or geographical location of a proposed action and may also be based on other criteria that would promote public awareness of proposed actions. The website must provide a summary of the impact assessment and a link to a source for the complete impact assessment.

(2) If due to time constraints a state agency is compelled to take an action allowed by this part before completion of an impact assessment, it shall, within 3 days of learning of the requirement to take the action, post notice of the action and provide a brief explanation of the action, the need for expedited action, and an estimate of when the action will be completed and the expected availability of the completed summary and impact statement.

(3) Unless the action may be taken without a completed impact statement as provided in this part, the state agency may not take the proposed action until it has completed and posted the impact statement.

(4) The state agency shall update the assessment and provide notice to the public if the action is not adopted before the 180th day after the date the original notice was given.

History: En. Sec. 1, Ch. 286, L. 2011.