Montana Code Annotated 2013

Clickable Image


     18-2-208. Exceptions. (1) The provisions of this part do not apply to money loaned or advanced to a contractor, subcontractor, or other person in the performance of the work.
     (2) A city or town may impose any other or further conditions and obligations in the security that is considered necessary for its proper protection in the fulfillment of the terms of the contract and not in conflict with this part.
     (3) The notice required by 18-2-204 to be given within 90 days after completion of the contract and acceptance of the work may not be construed to prevent or delay the payment of money due the contractor under the terms and conditions specified in the contract.

     History: (1)En. Sec. 1, Ch. 20, L. 1931; re-en. Sec. 5668.41, R.C.M. 1935; Sec. 6-401, R.C.M. 1947; (2), (3)En. Sec. 4, Ch. 20, L. 1931; re-en. Sec. 5668.44, R.C.M. 1935; amd. Sec. 1, Ch. 96, L. 1941; amd. Sec. 1, Ch. 175, L. 1957; Sec. 6-404, R.C.M. 1947; R.C.M. 1947, 6-401(part), 6-404(part); amd. Sec. 8, Ch. 130, L. 1995.

Previous Section MCA Contents Part Contents Help Next Section